Contractor on the Spot for 'Shoddy' Work at Lunga Lunga Border Post

By Farouk Mwabege

The contractor hired to build the Lunga Lunga one-shop border post left the site without completing the parking lot and buildings, an East Africa Legislative Assembly MP said Wednesday.

Despite the cost rising from Sh469 million to Sh633 million, the contractor did not renovate the old border post or install scanners, Ms Judy Pareno said.

While the border post on the Tanzanian side is built to specification, the one on the Kenyan side is incomplete.