Ministry approves re-designed office block

The Minister of Finance and Development Planning, Mr Kenneth Matambo is aware that the construction of a revenue office and six staff houses at Hukuntsi Sub-district that was scheduled to start in April 2015, has not yet started.

Mr Matambo said there was a delay in the completion of the design of the Hukuntsi revenue office block. He noted that the original design was rejected by his ministry in September 2014 as it was unsuitable for purpose and above budget.

However, he said the consultants working with DBES were requested to re-design the office block. He stressed that the re-designed office and six staff houses had since been approved and tender documents were being finalised.