Construction of 75km Nsc II Pipeline Delays


[Government of Botswana]The construction of a 75km North South Carrier pipeline from Moralane to Palapye has been delayed, says the Department of Water Affairs project officer, Mr Jonase Ramosalagadi. Briefing councillors during a Palapye special sub council meeting , Mr Ramosalagadi said the project was 27 per cent behind schedule. He said the project was currently 41 per cent complete instead of the expected 68 per cent. A number of factors contributing to the delay, he said, included issuance of visa and work permits for speci